Timeline
This page shows the construction progress of the MIC cleanroom
Timeline
Progress |
Timeline |
Installation |
Details |
100% Design Drawing |
03/07/2021-05/10/2021 |
|
|
Contactor Bid |
05/10/2021-07/29/2021 | ||
Detailed Construction Plan Creation |
07/29/2021-10/15/2021 | ||
Construction Progress |
10/18/2021-present | Start up of Instruments in progress | |
Utility Status |
|||
House Vacuum |
Installed | Y | Startup completed |
Toxic Gas Monitoring System |
Installed | N | Pending final calibration |
Gas Cabinets |
Delivered | Y | Pending startup |
DI Water System |
Installed | Y | Startup completed |
Steam Generator |
Installed | Y | Startup completed |
Air Compressor and Dryer (House CDA) |
Installed | Y | Startup completed |
Instrument Status |
|||
AirControl wet benches |
Installed | Y | Start up completed |
Hot plates and Ultrasonic Cleaner delivery |
Installed
|
Y | Start up completed |
Bruker profilers delivery |
Installed
|
Y |
Start up completed |
Laxco microscope delivery |
Installed
|
Y |
Start up completed |
Gamry Potentiostat |
Installed
|
Y | Start up completed |
Tecan Plate reader and Plate Washer |
Delivered
|
N | Pending installation |
KLOE Mask Aligner and Laser Writer |
Installed
|
Y |
Start up completed |
AJA E-beam/Thermal Deposition System |
Delivered
|
N |
Pending installation |
Oxford ICP-RIE System |
Delivered
|
N |
Pending installation |
MSI Probe Station |
Delivered | N | Pending installation |
Wire Bonder |
Installed | Y | Start up completed |
Chemical Cabinets |
Delivered | Y | Installed |